BISHOPS SUTTON (UNITED KINGDOM) PHOTOVOLTAIC SOLAR PLANT

Project description

Detail and key figures

Electromechanical Assembly and civil work for the Bishops Sutton solar plant in the United Kingdom, with a capacity of 12 MWp.

  • EPC.
  • Customer: O.P.D.E.
  • Price: more than 5 M€.
  • Time for completion: January - March 2014.

Main characterictics:

    B.O.S implementation of the solar plant, including:

  • Civil Works.
  • Assembly of metal structure support and photovoltaic modules (47.616 units).
  • Complete LV electrical installation.
  • Supply and assembly of transformation and inverter centres (7 units of 1,360 KVA, 1 unit d 540 KVA).
  • Electrical installation of MV at 33 kV to the connection point with the electric company.
  • Scada and monitoring system; Weather stations (2).
  • CCTV security system with thermal cameras and intelligent video analysis; Satellite communications
    system; Engineering.