logo

INVESTMENT PROJECTS OF ELECTRICITY AND INSTRUMENTATION OF CARTAGENA PETRO-CHEMICAL COMPLEX

Project description

Detail and key figures

Contract for investment project in improving and adapting the electrical and instrumentation installations of the petrochemical complex of Repsol in Cartagena.

  • Customer: REPSOL PETRÓLEO. S.A.
  • Annual price: €2,000,000.
  • Time for completion: 2013 - 2015.
  • Location: Cartagena, Murcia Region (Spain).

Main characterictics:

  • Performing more than 300 investment projects.
  • An average of 40 employees, reaching 90 employees in production stoppages.
  • Refurbishment and adaptation of 4 substations of the complex.