LAYING OF HIGH VOLTAGE AIR POWER LINE BESCANO-SANTA LLOGAIA

Project description

Detail and key figures

Laying of cable sections T2 and T3 for the high voltage air power line of 400 KV between Bescano and Santa Llogaia.

  • Owner: Red Eléctrica de España.
  • Price: 3.6 million euros.
  • Time for completion: last quarter of 2013 (7 months).
  • Location: Girona (Spain).

Main characterictics:

  • Line Length: 24 Km.
  • Line type: quadruple circuit, Simplex.
  • Cable: Condor.