SUPPLY POWER LINE OF THE BREÑA II DAM (CORDOBA)

Project description

Detail and key figures

A substation will be built consisting of a line output function of two 220 kV and two transformer functions 220/11 kV of 50 MVA each, for interconnection with the Pumping and Turbine Station of the dam and a high-voltage line of supply and evacuation of electricity, of 9.6 kilometres long with 33 supports. The connection point is made in the substation of Almodóvar del Rio property of REE (Spanish Electricity Network).

  • Owner: Sociedad Estatal Aguas de las Cuencas de España (Acuaes).
  • Price: €3,588,029
  • Time for completion: 16 September 2014 - Last quarter 2015 (12 months).
  • Location: Spain.