Detail and key figures

  • EPC.
  • Owner: EDP Renováveis.
  • Price: 3.385.000€.
  • Time for completion: 2012.
  • Location: Spain.

Main characterictics:

  • 1500 wind turbines of 17 AW with a rated capacity of 1,500 KW p/u (25.5 MW).
  • Civil works: Wind turbine foundations, building of assembly platforms, roads (10 km), pipes, foundation of the meteorological tower, horizontal drilling.
  • Electrical work: MV lines (53,000 m), fibre optic communication lines (20,000 m), earthing network (12,000 m of bare copper wire).
  • 132/12 KV Substation: Electromechanical engineering, civil works and electrical and medium and high voltage mechanical works.