logo

WORKS ON THE ELECTRIC LINE OF MEDINA DEL CAMPO – SALAMANCA

Project description

Detail and key figures

Implementation of the construction project works of electrification for the Medina del Campo-Salamanca-Fuentes de Oñoro line. Medina del Campo-Salamanca section. Substations and transformer stations associated.

The works of this project are located along the existing conventional gauge railway line between Medina del Campo-Salamanca-Fuentes de Oñoro. Medina del Campo-Salamanca section.

  • Owner: ADIF (Spanish administrator of railway infrastructures)
  • UTE (Joint Venture): EIFFAGE ENERGÍA and CHM
  • Price: More than 12 million euros
  • Time for completion: January 2014 (24 months).
  • Location: Valladolid - Salamanca.

Main characterictics:

  • Two-phase electric traction substation (220/±27, 5 kV, 2 x 30 MVA) in Pitiagua.
  • Two stations of intermediate self-transformation (55/27,5 kV, 1 x 10 MVA).
  • Two stations of final self-transformation or neutral zone (55/27,5 kV, 2 x 10 MVA).
  • Overhead high voltage line of 220 KV, double circuit, 20 km.
  • Remote control of power installations.

Related Projects