Project description
Detail and key figures
- Owner: Forma Seis.
- Location: Zaragoza.
Work performed:
- Cooling power installed: 1,164 kW.
- Heating power installed: 1,150 kW.
- Production of cold water through air condensing chillers.
- Production of hot water through low temperature boilers.
- Four water distribution pipes and variable water flow rate.
- Primary Air Handling Units with energy recovery.
- Fan coil type terminal units in offices.
- Centralised consumption metering system.
- Mechanical ventilation.
- Centralised Technical Management System.